Sitework


October 16 - November 12, 2014

It took about a month to prepare the site for the house and driveway. We had to make a little bit of a dent in the jungle and remove a pile of lava rock. Our sitework contractor, Moore's Excavation, did a fantastic job saving as many trees as possible!

First, George needed a dry spot to get out of the rain.












  








 Then the small equipment arrived for the initial tree clearing.



 






























The driveway was opened up to allow the bigger equipment in.





















Once the trees were cleared, it was time to take out some rock.
















 We used the rock that was removed on the driveway.

 




























Next, the septic tank was installed.



















 And the driveway and house site were compacted.